What Should a Builder Payment Schedule for a House Extension Include?

Home > News > What Should a Builder Payment Schedule for a House Extension Include?
Finished extension in Greenwich seen from the patio, with the timber folding doors open

A builder payment schedule sets out when you pay and what needs to have happened before each payment is due. On a house extension, the clearest schedules link each payment to a defined stage of work that both sides can check, and they are agreed in writing before work starts. This guide covers what to ask at quote stage and what to settle before you sign.

At quote stage: what to ask

You do not need a full contract at this point, but you should understand how the builder expects to be paid. Ask:

  • How are payments normally structured, and what triggers each one?
  • Is a deposit requested, and what does it cover?
  • Are any items bespoke or ordered well in advance, such as glazing or fitted joinery, and how are they paid for?
  • Do the prices include VAT, where VAT applies?
  • How are changes priced once work is under way?

The answers let you compare quotes on more than the headline figure. The renovation quote comparison checklist covers the rest of that comparison.

Before work starts: what to put in writing

Citizens Advice suggests getting the details of the job, including how and when you will pay, agreed in writing before building work begins (Citizens Advice). A written building contract should make clear:

  • each payment milestone and what must be complete for it to fall due
  • how completion of each stage will be evidenced
  • how variations are agreed
  • how any deposit and payments for bespoke materials are recorded
  • whether figures include VAT
  • how snagging, handover and the final payment work
  • any retention, if both sides have agreed to one

Defining stages and evidence

A stage number means little unless both sides agree what it covers. The house extension timeline guide shows the usual order of work, which helps when naming milestones. A practical milestone trigger names something visible and checkable, for example:

Payment due when the roof structure is in place and the extension is weathertight, confirmed on a joint walk round with photographs shared by the site lead.

Evidence might include photographs, a walk round or delivery notes for ordered items. A building control inspection is a separate matter. It relates to building regulations, it is not a blanket certificate that the contract work is complete, and it does not replace the payment terms you agreed.

Deposits and bespoke materials

Guidance from NCC on deposits and stage payments encourages agreeing what any upfront payment is for before work starts (NCC). Where a deposit relates to bespoke materials, ask for the order confirmation or supplier reference so the payment can be matched to the item.

Variations

Changes are common on extensions. Agree each variation in writing, setting out the change, its effect on the price and its effect on the programme, before the work is carried out where that is practicable. If something has to be done urgently, record it in writing as soon as possible afterwards.

Snagging, handover and the final payment

Agree what the final payment relates to. The contract should say how snags are listed, how they are signed off, what happens at handover and when the final payment is due. A retention, where part of a payment is held back for an agreed period, applies only if it has been agreed.

Example: an invoice that does not match the site

An invoice arrives for the first fix stage, but one room has not yet been reached. Check how the contract defines that milestone, then raise the point with the builder promptly and in writing, describing what you have seen. Do not assume you are automatically entitled to withhold payment, and do not set aside the payment terms you signed. If the wording is unclear, discuss it and record what you agree. If a disagreement cannot be resolved, Citizens Advice can help you understand your options.

Short checklist

Back to News Back to News